Schedule Post-Acquisition Processing Tasks

You can configure softWoRx so that specific processing tasks will occur after the images have been acquired. You can choose to either run these tasks automatically, immediately following image acquisition, or run the tasks manually using softWoRx Queue Manager to activate the queue.

To set up post-acquisition processing tasks:

1.  Click the Experiment Icon_Experiment.jpg icon in the Resolve3D main menu to display the Design/Run Experiment window.

2.  In the Design/Run Experiment window, click on the Run tab.

3.  Click on the Schedule Post-Acquisition Processing Tasks button. The Post Processing Options window is displayed.

4.  Activate the Enable Post-Acquisition Processing check box. If you want the post-acquisition processes to begin immediately after the acquisition is completed, activate the Automatically Run the Queue check box.

Design_Run_PostAcq_PostProcessingOptions_callout_sm.jpg

If you do not activate the Automatically Run the Queue check box, the selected post-acquisition processes are simply placed in the queue. You can subsequently run the processes from the softWoRx Queue Manager.

5.  To begin adding post-acquisition processing tasks to the task list, click on the first task to view a drop-down list of available options.

Design_Run_PostProcOptions_dropdown_callout_sm.jpg

The options on this drop-down list are identical to the options available in Task Builder. Select the processing option for the first post-acquisition task and click the Add button to add the next task to the list.

6.  Use the Options button next to each task to view and configure options specific to the selected task.

7.  When you are finished adding post-acquisition tasks to the list, click Done to close the Post Processing Options window and return to the Design/Run Experiment window.
Depending on your selections, the selected processing tasks will either be performed immediately after the acquisition, or placed in the queue for processing.