To save files to a DMS database during post-acquisition processing:
1. Click the Experiment
icon in the Resolve3D main menu to display the Design/Run Experiment window.
2. In the Design/Run Experiment window, click on the Run tab.
3. Click on the Schedule Post-Acquisition Processing Tasks button. The Post Processing Options window is displayed.
4. Activate the Enable Post-Acquisition Processing check box. If you want the scheduled post-acquisition processes to begin immediately after the acquisition is completed, activate the Automatically Run the Queue check box.
If you do not activate the Automatically Run the Queue check box, the selected post-acquisition processes are simply placed in the queue. You can subsequently run the processes from the softWoRx Queue Manager.
5. Click on the drop-down list in the Task field to view the available options. (The options on this drop-down list are identical to the options available in Task Builder.)
6. Select Save to DMS and click the Add button to add the task to the list.
7. Click the Options button next to the Save to DMS selection. The Save to DMS Options menu is displayed.
8. From this menu, select the Project and Dataset to which you want to save the data on the DMS database. You can optionally select the Category Groups and Category for the saved image data and add initial annotation to the file for future reference. When you are satisfied with the image data to be uploaded, click OK.